Short answer: By California law, your city must approve or deny a complete ADU permit application within 60 days. As of January 1, 2026, the city also has 15 business days to confirm your application is complete. In practice, a straightforward ADU on a flat lot is permitted in about 8 to 12 weeks; projects that need LADWP power upgrades or hillside clearances can take 4 to 6 months. Starting with a permit-ready plan set is the fastest way through plan-check.
The ADU permit process, step by step
- Get permit-ready plans drafted to California and Los Angeles building code.
- Submit your application to your city or county building department.
- Completeness check — the city confirms your application is complete within 15 business days.
- Initial plan check — city review, typically 2–4 weeks.
- Corrections & resubmittal — address any plan-check comments, usually 1–3 weeks.
- Agency clearances — LADWP (about 3 months if a power upgrade is needed), Bureau of Engineering, and Fire for hillside lots.
- Permit issued — pay fees and receive your permit, 1–3 days after approvals.
- Build & inspections — construction with staged city inspections.
Typical ADU permit timeline in Los Angeles
| Phase |
Typical duration |
| Application submission |
1 day |
| Completeness check |
1–15 business days |
| Initial plan check |
2–4 weeks |
| Corrections & resubmittal |
1–3 weeks |
| Agency clearances |
4–12 weeks |
| Permit issuance |
1–3 days |
A simple flat lot with no LADWP upgrade is often permitted in 8–12 weeks; LADWP, Bureau of Engineering, or hillside clearances can push the total to 4–6 months.
What affects your timeline
- LADWP electrical service is usually the biggest variable — about 3 months when a service upgrade is needed.
- Hillside or limited-access lots add Fire Department and grading reviews.
- Correction cycles — incomplete or non-compliant plans trigger extra rounds of review.
How to speed up ADU approval
- Start with a permit-ready plan set drafted to California and LA code — it clears plan-check with fewer corrections.
- Submit a complete application the first time.
- Use a permit-expediting service to manage submittals and corrections for you.
Frequently asked questions
How long does it take to get an ADU permit in Los Angeles?
A straightforward ADU is usually permitted in 8–12 weeks. By law the city must approve or deny a complete application within 60 days, though LADWP or hillside clearances can extend the total to 4–6 months.
Do I need a permit for an ADU in California?
Yes. Every ADU, including a garage conversion, requires a building permit. Plans must be drafted to California and local building code and submitted for plan-check.
What is the 60-day ADU rule?
State law requires a city to approve or deny a complete ADU permit application within 60 days. If the city misses the deadline, the application can be deemed approved.
Can I speed up the ADU permit process?
Yes. Start with a permit-ready plan set, submit a complete application, and consider a permit-expediting service to manage corrections.