ADU timeline for Los Angeles: design, permitting, and construction phases, total time from start to move-in, and how to build faster.
Get a Free Quote| Phase | Typical duration |
|---|---|
| Design & plans | 2–6 weeks (about 1 week with a pre-designed plan) |
| Permitting (plan check + clearances) | 8–12 weeks |
| Construction | 3–8 months |
| Total | 6–12 months |
| ADU type | Construction time |
|---|---|
| Garage conversion (300–500 sq ft) | 3–4 months |
| Small detached ADU (400–600 sq ft) | 3–4 months |
| Large detached ADU (800–1,200 sq ft) | 6–8 months |
Most ADU projects take 6 to 12 months from start to finish: about 2–6 weeks for design, 8–12 weeks for permitting, and 3–8 months for construction.
A garage conversion usually takes about 3–4 months to build, plus design and permitting time.
Use a permit-ready plan set, prepare your property documents early, respond quickly to questions, and hire an ADU-experienced team.
Permitting typically takes 8–12 weeks, though simple flat lots can clear in about 4 weeks and hillside lots can take 3–4 months.